Business hour settings

Business hour settings

In any project, a task's Start Date, End Date, Start time, End Time and Duration are calculated based on it's Business Hour configuration.

Feature Availability: Premium and Enterprise plans

Calculation of Task Duration Based on Working Days

Calculation of Task Duration based on Start Date and Due Date

The task Duration is calculated depending on its Start Date and Due Date. A task's Start Date and Due Date will always be considered as a working day, when manually selected, even if it falls on a weekend or a holiday.

Example: Task A starts on September 14,2013 (Saturday) and ends on September 15,2013 (Sunday), hence it's task Duration will be 2 days.

Calculation of End Date based on Start Date and Duration

The Due Date of a task is calculated depending on it's Start Date and Duration. A task's Start Date will always be considered as a working day, when manually selected, even if it falls on a weekend or a holiday. However, it's Due Date is automatically calculated skipping the weekend and holidays based on the Business Hour settings.

duration-enddate

Example: Task B starts on May 12, 2018 10:00 AM (Saturday) with a Duration of 367 hours, it's Due Date will fall on July 16, 2018 05:00 PM (Monday). Since the weekends are excluded in the Business Hour settings they will not be considered when calculating the end date.

skip-weekends

Calculation of Task Duration Based on Working Hours

Task duration can be calculated for any combination of working hours assigned to a task. Listed below are some real time task calculations in project management based on different combination of working hours assigned to tasks.

Presume the Business Hours setting is configured between 10 am to 6 pm for tasks in an organization.

Task Start Time is before Business Start Time

If you set the start time of a task before the scheduled business start time, the task duration is calculated from the start time of the task till the task end time.

Example:
If Task A starts at 8 am, the working hours of the task will be 5 hours. This is calculated from the start time of the task which falls at 8 am till the end time of the task 1 pm, which adds up to 5 hours.


Task Start time is after Business End Time

If you set the start time of a task after the scheduled business end time, the task duration is calculated from the start time of the task till end of the day, i.e 12 am.

Example:
If Task A starts at 8 PM on 9th of July, 2018 and ends at 3:00 PM on 10th of July, the duration is calculated as start time of task to end of day (08:00 PM to 12:00 AM, 4 hours) plus start time of next business day till end time of task (9:00 AM to 03:00 PM, 6 hours) which totals 10 hours.


Task End Time is Before Business Start Time

If you set the end time of a task before the scheduled business start time, the task duration is calculated from the day's start time i.e 12 AM till the task's end time.

Example:
If the end time of Task A is 6 am, the working hours of the task will be 8 hours. This is calculated from the start time of task till end of business day (4:00 PM to 5:00 PM, 1 hour) plus end of day till the task end time (12:00 am to 6:00 am, 6 hours), which adds up to 7 hours.


Task End Time is After Business Start Time

If you set the end time of a task before the scheduled business end time, the task duration is calculated from the scheduled start time till the end time of the task.

Example:
If the end time of Task A is 3 pm, the working hours of the task will be 6 hours. This is calculated from the scheduled business start time of the task (9 am), till the task end time (3 pm), which adds up to 4 hours.

endtime-afterbusiness

    • Related Articles

    • Org settings

      Configuration Update Portal Logo Click  in the top band. Navigate to Portal Configuration > Org Settings > Configuration > Portal Settings tab. Click the Upload button. Click Choose File and select an image from your local computer. Click Upload. You ...
    • Set up your business

      When you log in to your Zoho Bookings account for the first time, you will arrive at the business setup page. The setup page will guide you through three steps in order to configure your work preferences. You can change these settings at any time ...
    • Business hours in templates

      Business Hours settings help you to calculate the task duration based on your settings. When you choose an existing project / task template for a real time project, all its tasks, milestones, forums and comments are shifted based on the Project Start ...
    • Manage Business Preferences

      The Manage Business icon in the top menu bar is your go-to for managing all of your booking preferences. This page covers general settings. To edit business details, Click Manage Business in the top menu bar. Note that under the General tab, Basic ...
    • Privacy Settings

      Privacy Settings You can configure your privacy settings to manage the data that is collected and stored in Zoho Lens. Privacy settings let you consent to data gathered and processed from third-party services, limit usage through role-based access ...