Baseline comparison gives an insight on the open tasks and the total time spent on them. Create baselines to compare and analyze project changes over a given time period. Navigate to a project and then select Gantt & Reports > Milestone Gantt. ...
You can set a baseline with the help Milestone Gantt chart. Navigate to a project and then select Reports > Milestone Gantt. Click in the upper right corner. Click Set Baseline. Enter the baseline name and click Set Baseline. A baseline is ...
Navigate to a project and then select Reports > Milestone Gantt. Click in the upper right corner. Hover over the baseline and click . Enter a new baseline name. Click Save. Hover over the baseline and click to delete a baseline. Deleting a ...
End variance tracks the delay in the completion of tasks. It is the difference between the baseline finish date and the current end date of the task. Baseline finish date is the initial estimated task completion date.
Slippage tracks the tasks that haven't started yet. It is the difference between the baseline start date and the current start date of the task. Baseline start date is the original start date of the task. Navigate to a project and then select Gantt & ...